PJM Interconnection just filed the plan I've been waiting for someone to file. On Monday, the operator of the largest US grid proposed combining its separate studies for power plants, transmission, and data centers into a single process, cutting the review timeline from two years to 12 months. That's a real, structural attack on the single biggest obstacle to energy abundance in America: a bureaucratic queue that takes longer to clear than it takes to pour concrete for a reactor.
This is a proposal, not a done deal. PJM is asking the Federal Energy Regulatory Commission for a 60-day comment period and a ruling within 120 days, which means the earliest this changes anything on the ground is well into next year, and only if FERC approves it as filed. The Data Center Coalition already pushed back in October, warning the combined process could complicate rather than simplify interconnection, according to the same Reuters report. So treat "12 months instead of 24" as a target PJM is fighting for, not a number the grid has delivered.
Somebody Has to Pay for the Speed, and PJM Just Said It Won't Be Everyone
Here's the part that matters more than the timeline: PJM wants states and utilities to bill data center companies directly for the transmission upgrades their load requires, instead of spreading those costs across the 67 million people the grid serves, per Reuters. That's a direct response to a supply shortfall PJM itself pegs at roughly 6.8 gigawatts. It's also a response to mounting political heat — the grid's independent market monitor flagged Thursday that data center-driven costs could add another $5 billion to $10 billion to next year's capacity auction, stacking on top of $29.4 billion in costs the same watchdog called already "irreversible."
I don't think the answer is to slow down the data centers. I think the answer is exactly what PJM is attempting: get new generation connected faster, and make the companies pulling the gigawatts pay for the wires they actually need. Natural gas still supplies nearly 40% of US generation and nuclear another 17%, according to the IEA — there's no abundance future that skips building more of both while the queue clears faster.
Watch what FERC does with this filing over the next four months. A ruling that approves the combined study process and the cost-allocation shift would be the clearest signal yet that regulators are choosing throughput over gridlock. A watered-down version keeps America's AI buildout bottlenecked by paperwork, not physics — the one bottleneck that should never be allowed to stand.